POWER
GENERATION FACILITY
Power Generation Facility Burner Upgrade
Replacement and upgrade of 12 burner sections
6
month shutdown
60
Electricians on the project
150,000
feet of cable with 6000 terminations
1000
feet of cable tray installed
Job
completed on schedule with zero injuries
Mobilization
of employees from Delaware and New Jersey
12
hour shifts 7 days a week during major shut down times
|