Solvay Solexis

Floating Tank Roof Repair/Replacement

Scope of Work

The counterweights for the floating roof broke loose and sheared off.

Project Details

In order to make the roof operational again, the roof had to be removed so the counterweights could be repaired.
We designed a lifting plan to facilitate the removal of the 45,000 pound roof. We designed the lifting beam and then fabricated and tested it. We executed our plan and removed the roof safely.