INDUSTRY: Technology/Other KEY SERVICES UTILIZED: Rigging, Plumbing, Electrical |
|||
|
<< PREV CASE STUDYNEXT CASE STUDY >>
PROJECT NAME OR TYPE:Powerhouse Installation PROBLEM OR TASK:Install boilers, economizers, DA tank, and other components OUR SOLUTION OR DESCRIPTION OF WHAT WE DID:The powerhouse consisted of two new 100,000 lbs/hr boilers, new economizers, DA tank and condensate receiver with feed water pumps along with all new level and flow controls to make a complete operating plant. The boilers were shipped on railroad cars and required a 600 ton crane to off-load. UNIQUE CHARACTERISTICS OF OUR WORK:Planning and implementation of this complete project without impeding ongoing operations. Completion on time and within budget. |
||